Back to a Quick Look |
Setup Inspection. A requirement for inspection consists of defining on a Job for an Item (viz a group which is NOT a work package), the Work Packages (viz groups defined as such) which Inspections Tasks are required. |
|
Back to a Quick Look |
Record Inspection. Having selected the Item to be inspected, and the Work Package for which an Inspection Task has been carried out, the report may be entered specifying:
The results of any previous inspections can be viewed. |
|
Back to a Quick Look |
Manage Inspections. The results of an inspection need to be communicated to both an Inspector (for inspection) and the Work Package Contractor (for rectification if reinspection is needed). In addition, after a Work Package Contractor has carried out any rectification, then this needs to be recorded to enable reinspection to be carried out. The date that an Inpection Report was issued to the Work Package Contractor, and the date the Work Package Contractor advised clearance of the defect. The date that the Inspection Report was sent to a Works Contractor are recorded when the report is generated and sent. |
| Continue
to Key Event Dates A Quick Look at TDOC 16 of 19 - Open TDOC Web Site |
|